Construction images
Construction of BM16 with the dates and images of some milestones.
January 2017: the spectrometer is operational



September 2016: mirrors installation
M1







M2



July 2016: mirror vessels installation
M1


M2




June 2016: table installation




December 2015: E4 and absorber installation


October 2015: Monochromator installation
The monochromator is now installed, ready for cabling and cooling.




June 2015: E1 vessel installation
The vessel containing the first vertical and horizontal slits is installed.
May 2015: ground preparation for the monochromator
The concrete soil is excavated and marble is installed.


May 2015: beam shutter installation
Olivier and Cyril guiding the densimet block into the beam-shutter vessel.

The beam-shutter is at its final position at the end of OH1 hutch.

May 2015: slits preparation
Densimet slit blades are machined, fixed on the copper structure and aligned.


March 2015: installation of the frames for the slit vessels

February 2015: first radioprotection tests
The beam goes through RV0 and the delimiter and the OH1 hutch is safe.


January 2015: installation of RV0 and delimiter
The delimiter is installed and equiped with a cooled Be window to perform radiation tests.


September 2014: lead hutches installation
Former spanish beamline has been partially dismounted and two new hutches are built.